The Details

PROJECT OVERVIEW

IDES Electrical Services were appointed by Lanes Group to design and install Solar PV systems across four buildings at their Eccles depot facility. The project formed part of the company’s wider sustainability strategy, helping to reduce carbon emissions, improve energy efficiency and increase the use of renewable energy across the site.

THE CHALLENGE

The project involved the design and installation of four separate Solar PV systems across multiple operational buildings within a live depot environment. The works required careful planning and coordination to ensure minimal disruption to day-to-day operations, with strict health and safety procedures implemented throughout the project, including segregation measures and controlled working areas.

In addition to the installation works, IDES managed the DNO approval process and coordinated structural roof surveys to verify the suitability of each building prior to installation. The project was further complicated by roof overcladding works being undertaken by others, requiring close coordination between multiple contractors to maintain programme and safety requirements.

OUR SOLUTION

IDES delivered a complete turnkey Solar PV solution, managing the project from initial site assessments and system design through to installation, testing and commissioning.

The project comprised four independent Solar PV systems installed across four separate depot buildings, with a combined installed capacity of 165.9kWp. In total, 395 solar panels were installed, providing a significant source of renewable energy generation across the site.

Working closely with Lanes Group and other project stakeholders, IDES successfully delivered all systems while maintaining safe operations throughout the live working environment.

SERVICES DELIVERED

  • Complimentary Design, Site Assessment & Proposal
  • Solar PV System Design
  • DNO Applications & Approvals
  • Structural Roof Survey Coordination
  • Solar PV Installation
  • Installation Across Four Separate Buildings
  • Electrical Testing & Commissioning
  • Client Handover Documentation

PROJECT OUTCOME

The project was successfully completed within programme, providing Lanes Group with a substantial on-site renewable energy generation system capable of supporting the company’s long-term sustainability objectives.

The completed installation comprises four Solar PV systems with a combined capacity of 165.9kWp and is expected to avoid approximately 32 tonnes of CO₂ emissions each year. The project helps reduce reliance on grid-supplied electricity while supporting the client’s environmental commitments and reducing long-term energy costs.

KEY STATISTICS

  • 165.9kWp Total Installed Capacity
  • 395 Solar Panels Installed
  • 4 Separate Solar PV Systems
  • 4 Operational Depot Buildings
  • 32 Tonnes of CO₂ Avoided Annually
  • DNO Approval Process Managed by IDES
  • Structural Roof Surveys Coordinated by IDES

PROJECT DETAILS

Sector: Solar PV
Client: Lanes Group
Location: Eccles

About The Project